52 Solar Projects %u2013 Toolkit for warehouse owners and operators - 2025 EditionElectricity Network connection requirementsGrid connection permit For all solar PV projects an application for connection agreement with the distribution network operator must be submitted and granted. The tasks required to confirm the connection vary with the size of the generating plant. In general, the bigger the generator, the more complex the connection requirements. Engineering recommendations have been created by the Electricity Networks Association (ENA) and used by the network operators to support the management of a safe and reliable electricity network. Engineering Recommendation (EREC) G99Most solar PV projects in warehousing will fall under G99, which outlines the legal requirements for the connection of generation equipment to the distribution network including:%u2022 Projects with capacity more than 16A per phase.%u2022 Projects connected at a higher voltage than 230V(single phase) or 400V(three phase).%u2022 Any project not type tested under EREC G98.EREC G99 has two categories of relevance for rooftop solar project: type A applications for less than 1 MWp and type B applications for 1-10 MWp. A summary can be obtained from the Energy Networks Association (ENA).Following submission of the G99 application, the DNO has a statutory maximum response time of 45 days for low voltage energy devices and 65 days for high voltage energy devices to approve installation or make further contact about appropriate amendments needed (e.g. monitoring equipment or hardware).If your generation project could materially affect power flows at the GSP (the boundary point between the distribution and transmission networks), and headroom is limited, the timescale could be significantly extended (by approximately 6-12 months), due to the need for National Grid transmission to carry out a Statement of Works process. You should discuss the likelihood of a Statement of Works being required with your DNO at an early stage. Assessment and design fees can apply. DNOs elect to charge (or not) at different points in the application process. Although the process is short, the wait time can often be due to waiting for the DNO to get to your application in their queue of applications. The solar PV installer will support you through the application process. Once an application is made, the DNO will assess the impact on the grid and produce a time limited connection offer, which will included the conditions and additional costs required for the connection. If the offer is not accepted, it may not be reissued on the same terms, and any resubmission could be subject to reassessment and additional charges.Once accepted, the DNO must be provided information to show compliance of the technology with the connection permit. The developer will provide the DNO advance notification of commissioning and inform when commissioning has been completed.Engineering Recommendation (EREC) G100 Typically, a G99 application is submitted first to assess the feasibility of connecting the system to the grid. If the DNO determines that grid constraints prevent full export capacity, they may require compliance with G100. This means implementing an export limitation scheme to ensure that exported electricity does not exceed the stipulated limit.SummaryConnection permits can be a major barrier for solar PV projects in certain areas and particularly for larger projects. It is therefore important to complete the application as early as possible and to engage from an early stage with the relevant DNO to identify potential network limitations. Recent reforms to the grid connection process aim to address these challenges by removing inactive (%u2018zombie%u2019) projects from the queue and prioritising deliverable, ready-to-build clean energy schemes. These changes are designed to improve access to limited network capacity and reduce delays for viable projects.